Construction of Tullo Wind Farm is expected to last nine months in total.
Phase one will take around two months and started on September 15th.
During this time, we will:
Phase two will last approximately seven months and will see:
Phase one will take around two months and started on September 15th.
During this time, we will:
- Establish a temporary construction compound,
- Lay access tracks, and
- Complete the site entrance.
Phase two will last approximately seven months and will see:
- Construction of a substation,
- Completion of access tracks,
- Installation of underground cables, and
- The building of the foundations on which the wind turbines will stand. The turbines will then be erected.